Re: New build in Superior Wi.

Unread post by Guest »

I’ve worked as fill in deck hand on miller’s other ferry’s past 2 summers. Covid created build delays. Last word is completion for delivery end of April. The trip to PIB is all planned n crew assigned. Subject to change of course.
Guest

Re: New build in Superior Wi.

Unread post by Guest »

Thanks for that information. Interesting to note that the original completion date was late 2019, which would have been pre covid.
Mr Link
Posts: 1198
Joined: December 6, 2014, 3:43 pm

Re: New build in Superior Wi.

Unread post by Mr Link »

Its the ferry Mary Ann Market for Miller Boat Lines of Port Clinton Ohio. Their website mentions a 2021 delivery. The initial press release back in 2018 said a late 2019 delivery so it is at least 15 months behind that schedule. Haven't heard why but Covid could have certainly played a part, both at the ship yard and with the need for a new boat by the ferry company. The pandemic could have also caused supply issues with key components.

Lots of photos and drawings here at Miller Boat Lines website:

https://millerferry.com/mv-mary-ann-mar ... e033c-4267
Guest

New build in Superior Wi.

Unread post by Guest »

There is a new boat that has been under construction for over two years at Frasier Shipyard. It looks like a ferry? It sure is taking a long time to complete. Was it being built on speculation or is it being built for someone? Is there a completion date?