any new info regarding Soo Locks construction

Discussion board focusing on Great Lakes Shipping Question & Answer. From beginner to expert all posts are welcome.
kirbyj0076

Re: any new info regarding Soo Locks construction

Unread post by kirbyj0076 »

the incident that closes the Poe lock for any reason will probably what will be required to spur them into action
Mr Link

Re: any new info regarding Soo Locks construction

Unread post by Mr Link »

The US Army Corps of Engineers estimates the earliest possible date for completion is 2020 if Congress finds the remaining $546,704,000.00 needed to finish construction. And with the project having an estimated benefit to cost ratio of 0.73 (73 cents worth of benefit for every dollar spent) it doesn't look like Congress is falling over backwards to fund the project. Much of what has been funded so far (design work, cofferdam work and approach dredging) has been funded as earmarked projects which don't have to pass any cost benefit tests.

A 2010 fact sheet can be found on page LRD-52 at:

http://www.usace.army.mil/CECW/PID/Docu ... 10_efc.pdf

Here is a summary:

Total estimated cost: $580, 264,000.00
Allocation thru fiscal year 2008: $15,591,000.00
Fiscal Year 2009 allocation: $17,000,000.00
Fiscal Year 2010 allocation: $ 969,000.00
Balance to Complete after FY 2010: $546,704,000.00

FY 2010 activities: Continue detailed design of remaining features and complete construction contracts awarded in FY 2009.
GaryJ

any new info regarding Soo Locks construction

Unread post by GaryJ »

Anyone know how the new lock construction
is proceeding up at the Soo? I know they
posted blasting and channel dredging notices
recently, whats the timeline progression as
to when the new enlarged lock will be fully
completed and operational ?

Thanks, GaryJ